Should the Developers accept changes during the sprint if Product owner asks?
In Sprint the Spring Goal is constant and the Sprint backlog can be changed as long as the Sprint Goal is not endangered. So I and my Developers will evaluate the change and accordingly we will make a call. First, I shall try to prioritize the new change without getting changes to the current Sprint, if not possible then I will take the above approach.