You are pushing for a critical user story to be selected for the next Sprint. But, the final front-end designs still are missing, but the UI designers promise to deliver no more than two days after the Sprint planning. The Scrum Master, however, rejects this idea; the work item is not ready to be selected for a Sprint. What can you do?
This is a pure negotiation with the Scrum Team. The answer depends on the team’s situation and experience: If the designers are likely delivering—they have always kept their promises in the past—, and the Developers could accomplish the user story nevertheless within the Sprint, and the Developers agree with the situation, it is probably an acceptable exception. Ultimately, the Developers decide how much work can be accepted into the Sprint.