During a Product Backlog Refinement/Sprint Planning, you find that your Developers are struggling estimate the backlog items. What will you do?
I will ask them if they are clear about the functionality of the backlog item. If there is any challenge in understanding the scope due the size of the user story being large, I will collaborate with them to see if it can be split into smaller using some techniques like: User role based splitting, simple to complex, data entry patterns etc techniques. Once the large backlog item is split into smaller, I and my Developers will discuss on the scope of each smaller story by discussing respective acceptance criteria so that they can estimate.