In case you receive a story on the last day of the sprint to test, and you find there are defects, what will you do? Will you mark the story to done?
The completeness of a User Story in a Sprint is purely decided based on the Definition of Done. For example if the Definition of Done says there should not be any severity 1 or 2 defects but it the Story has some lower severity defects such as cosmetic then the Product owner may accept that story and add the defects to the Product Backlog. If the defects are of severity 1 or 2 then it is not to be accepted and moved back to the Product backlog at appropriate location as per Product owner’s discretion. Accepting low quality stories that do not meet the Definition of done leads to illusion of progress.